Topics getting the most attention in Village of Mineola public meetings, ranked by how frequently they are discussed.
12 issues in water utilities
Lead Water Service Line Compliance
Governor Hochul awarded Mineola an $11 million grant to improve water infrastructure, including finding and replacing lead service lines — a major boost to water safety and the water fund.
PFAS treatment at Well No. 1
The village moved forward with removing 'forever chemicals' from its drinking water by awarding three contracts totaling about $6.9 million for treatment at Well #6 on Westbury Avenue. Wells 4, 7 and Level One have already been treated — this finishes the job.
PFAS treatment at Well 6
Two small change orders on the PFAS treatment plant at Well 1 (steel lintel and truss anchoring work) were approved without changing the contract total — drinking water safety work moving forward.
Water system infrastructure purchase
The village is spending $94,635 on 165 new water meters and radios, which keep billing accurate and the water system running. Separately, the well treatment project came in nearly $35,000 under contract.
Street lighting and LED conversion on Wellington Road
Residents say the Wellington Road streetlights are dim and some are out. The village is converting all lights to LED, working counterclockwise from the northeast, and Wellington is next; residents can report outages via the MyMineola app.
Water department staffing
Peter Diglio's promotion to water plant operator keeps a trained, newly licensed employee in the village's busy water department.
Water storage tank inspections
The village's two water storage tanks — one in-ground at Emory, one above-ground on Elm — are due for inspection, and the board hired engineers for $5,800 to check them out and write reports.
Downtown parking meter and utility modernization
New solar meters reduce lost revenue from broken meters, and GIS mapping replaces 1950s-era paper maps so crews can find shutoffs fast during water main breaks.
Sanitary Sewer Improvements Project design
The village is spending $35,000 to design sewer upgrades — early groundwork for infrastructure improvements residents depend on daily.
LED lighting at Mineola Memorial Library
An intermunicipal agreement with Nassau County will bring LED lighting to the Mineola Memorial Library.
Well No. 4 water treatment project
Three change orders totaling about $29,000 keep the PTAS treatment project at the Old Country Road/Eighth Avenue well on track, including SCADA automation and startup support.
2025 Annual Water Quality Report
The village hired engineers to produce the legally required annual water quality report for $8,300.