High PriorityWater Utilitiesopen

PFAS treatment at Well 6

Summary

Two small change orders on the PFAS treatment plant at Well 1 (steel lintel and truss anchoring work) were approved without changing the contract total — drinking water safety work moving forward.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 1, 2026.

Impact analysis

💰Financial impact

$7,700.40 in combined change orders funded from existing bid item five — no change to the overall contract amount.

✅Who benefits

All village water customers who benefit from PFAS-free drinking water.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Village of Mineola

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.