Road resurfacing program funding increase
Summary
Paving is 60%+ done, striping finished a month early, guide rail work is in year three of ten, and bridge projects in Swan Lake, Callicoon Center and Cochecton are moving forward — with a June 17 public meeting on Bridge 51.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 10, 2026.
Impact analysis
Paving is about $390,000 over budget on price escalations, partially offset by $280,000 more in state CHIPS aid.
Motorists on improved county roads and bridges.
Mentions & discussions (2)
Public Works Committee — September 10, 2026
The 2026 county road paving contract grew by about $750,000 from its original $7.25 million due to fuel and binder costs, but officials said existing budgeted funds cover it. Paving continues in Fallsburg on routes 52 and 56, with guide rail and drainage work added.
Public Works Committee — June 11, 2026
Paving is 60%+ done, striping finished a month early, guide rail work is in year three of ten, and bridge projects in Swan Lake, Callicoon Center and Cochecton are moving forward — with a June 17 public meeting on Bridge 51.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Sullivan County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.