Fiber crews are working through harsh winter conditions on County Route 92 near Tenana Lake. Complaints have been fixed within 24 hours, and officials praised coordination between Archtop, DPW and town crews.

At a glance

Total mentions
10
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 8, 2026.

Impact analysis

💰Financial impact

State broadband grant-funded; extension decision expected by September.

✅Who benefits

Residents in the affected areas who will get high-speed internet service.

⚠️Who could be affected

Travelers may face temporary disruptions on work routes during construction.

Mentions & discussions (10)

The River ReporterOct 27, 2026

Update on Sullivan County broadband project

Update on Sullivan County broadband project The River Reporter

MeetingOct 8, 2026

Management & Budget Committee — October 8, 2026

ITS reported strong progress on the countywide broadband project — 216 miles of conduit in, 120 miles of fiber placed — with inspections passing well and completion targeted by June 30, pending a budget increase request.

WAMCSep 28, 2026

‘Completely transformational:’ Inside Sullivan County’s high-speed internet buildout

‘Completely transformational:’ Inside Sullivan County’s high-speed internet buildout WAMC

Radio CatskillSep 24, 2026

‘Completely Transformational:’ Inside Sullivan County’s High-Speed Internet Buildout

‘Completely Transformational:’ Inside Sullivan County’s High-Speed Internet Buildout Radio Catskill

MeetingSep 10, 2026

Management & Budget Committee — September 10, 2026

Conduit is 82% done (207 of 253 miles), with completion targeted by end of 2025 construction season plus 2027 padding. CIO Green pushed back hard on claims of poor communication, citing 500+ daily construction notification emails since December and monthly municipal meetings.

MeetingAug 6, 2026approved

County Legislature — August 6, 2026

The county granted a permanent easement so telecom lines can be built and serviced, moving broadband expansion forward in Rockland.

MeetingJun 11, 2026approved

Management & Budget Committee — June 11, 2026

Crews have laid 93 miles of conduit and 44 miles of fiber, with the first five customers live in Liberty. Permitting delays have pushed the county to ask for a six-month extension to June 2027 on the project deadline.

MeetingMay 14, 2026

Management & Budget Committee — May 14, 2026

The county fiber project now has actual customers — it hit its year-end signup goal within two weeks of launch. 90 miles of conduit and 26 miles of fiber are in the ground, bringing work-from-home and connectivity to rural areas.

MeetingApr 9, 2026approved

Planning and Community Resources Committee — April 9, 2026

Fiber and conduit installation is ramping up now that the ground has thawed, with the first customer passes expected soon.

MeetingFeb 5, 2026

Planning and Community Resources Committee — February 5, 2026

Fiber crews are working through harsh winter conditions on County Route 92 near Tenana Lake. Complaints have been fixed within 24 hours, and officials praised coordination between Archtop, DPW and town crews.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Sullivan County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.