Auxiliary heat for Delancey Hall
Summary
The town is in the final stretch of paying out the Tundra Contracting job at Delancey Hall. This payment brings total contract spending to about $664,800, with only a small balance left to pay.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
This payment is $117,616.01, part of a contract totaling about $664,800.
Residents get the Delancey Hall project finished, with the contractor paid for verified work.
Mentions & discussions (2)
Town Board Meeting - Oct 13, 2026
The board weighed propane versus oil tank options ($6,925–$8,155) as backup for the heat pumps, but tabled the choice until more written quotes come in.
Town Board (Special) - Jul 20, 2026
The town is in the final stretch of paying out the Tundra Contracting job at Delancey Hall. This payment brings total contract spending to about $664,800, with only a small balance left to pay.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for North Salem, NY
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.