New York Record
Newburgh
Medium PriorityParks Recopen

Delano-Hitch Aquatic Center Contract Change

Summary

The aquatic center contractor, DJ Heating & Air Conditioning, will credit the city $7,904.02 after accidentally setting off the fire suppression system during construction, bringing the mechanical contract down to about $297,318.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jan 22, 2026.

Impact analysis

💰Financial impact

Reduces the mechanical contract by $7,904.02 to $297,317.69.

✅Who benefits

City taxpayers, who pay less for the aquatic center project.