Community Center construction progress
Summary
The governor visited September 18 to kick off a $2.8 million community center overhaul — HVAC, lighting, stage, kitchen, classrooms — with $1.13 million from a state grant. Senior groups are displaced to Tully Park for about eight months.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 23, 2026.
Impact analysis
$2.8 million total, with $1.13 million covered by a state capital improvements grant.
Seniors, scouts, the PAL, the MAA and Junior Fire Department groups that use the center.
Senior groups meeting Tuesdays and Thursdays are displaced to Tully Park during roughly eight months of construction.
Mentions & discussions (3)
Village Board of Trustees - Sep 23, 2026
The governor visited September 18 to kick off a $2.8 million community center overhaul — HVAC, lighting, stage, kitchen, classrooms — with $1.13 million from a state grant. Senior groups are displaced to Tully Park for about eight months.
Governor Hochul Announces Groundbreaking of $2.8 Million Mineola Community Center Renovations on Long Island
Governor Hochul Announces Groundbreaking of $2.8 Million Mineola Community Center Renovations on Long Island Governor Kathy Hochul (.gov)
Village Board of Trustees - Jul 8, 2026
The village awarded three contracts totaling about $2.9 million to renovate the Community Center, with construction expected to start within 60 days and last roughly 12 to 16 months. A state grant covers up to $1.1 million of the cost; residents should expect some construction inconvenience around the facility.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Village of Mineola
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.