A resident challenged why the unanimously approved demolition RFPs were scrapped after the election. The mayor said the election results showed no support for demolition and the village will pursue a landmark plan instead.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 6, 2026.
Impact analysis
Avoided up to $90,000 in demolition assessment costs; demolition itself was estimated in the millions.
Those favoring preservation of St. Paul's under a landmark plan.
Residents who wanted the demolition costs formally assessed feel their request was abandoned.
Mentions & discussions (2)
Board of Trustees (Regular) - Apr 6, 2026
A resident challenged why the unanimously approved demolition RFPs were scrapped after the election. The mayor said the election results showed no support for demolition and the village will pursue a landmark plan instead.
Board of Trustees (Regular) - Mar 19, 2026
The day after village voters backed preservation roughly 60-40, trustees unanimously ordered the Building Superintendent to stop all work on a demolition RFP. Seven firms had quoted $0 to $90,000 just to inspect and bid, and no bids were pursued. Preservationists say restoration costs have grown from $910,000 in 1993 to about $10 million today.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Village of Garden City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.