Crescent Avenue Bridge replacement
Summary
Bridge construction won't wrap up until the second week of July, which will complicate access to Amsterdam Mohawks baseball games. The council wants message boards updated with directions on how to get in and out of the park.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Apr 21, 2026.
Impact analysis
About $2.2 million total, leaving roughly $500,000 in CHIPS money in reserve.
Once done, the bridge gets a new two-lane span with sidewalks to modern standards.
Mohawks fans and Shuttleworth Park visitors face detours and access confusion during the first half of the season.
Mentions & discussions (4)
Common Council - Apr 21, 2026
The ~$2.2 million paving program starts in early May, with $156,000 for the city's 5% match on the Crescent Avenue Bridge, which should reopen in July.
Common Council - Apr 7, 2026
The bridge replacement is moving fast — steel girders go up the week of April 13, with staging on Pioneer Street taking a lane, and substantial completion targeted for July.
Common Council - Mar 3, 2026
Bridge construction won't wrap up until the second week of July, which will complicate access to Amsterdam Mohawks baseball games. The council wants message boards updated with directions on how to get in and out of the park.
Common Council - Jan 6, 2026
The bridge is on track to reopen in July; the wastewater plant upgrade is at 95% design with state review underway.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Amsterdam
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.