CDBG Demolition Project Nears Completion

Summary

The demolition project is on track to finish by the end of March, with two extra structures added to the contract — including 21 Axon Street — paid from the demolition line.

At a glance

Total mentions
7
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Oct 20, 2026.

Impact analysis

💰Financial impact

About $90,000 in added demolition work funded from the demolition line.

✅Who benefits

Neighborhoods near blighted properties that get torn down.

Mentions & discussions (7)

MeetingOct 20, 2026

Common Council - Oct 20, 2026

The city has demolished 23 structurally unsound buildings using $1 million in federal CDBG funds, with the grant nearly ready to close out. A public hearing on the project drew no public speakers.

MeetingOct 6, 2026discussed

Common Council - Oct 6, 2026

The city plans to spend $1 million in federal CDBG money demolishing 23 structurally unsound buildings. A public hearing on the plan is set for October 20 at 5:50 p.m.

MeetingAug 18, 2026

Common Council - Aug 18, 2026

Years after a building collapse, a pile of bricks still sits beside the creek, threatening to slide in. The city wants federal CDBG money to clean it up and open the site for future parking and development.

MeetingJul 7, 2026

Common Council - Jul 7, 2026

The building whose roof caved in last year is now officially "slum and blight," and the council is the SEQRA lead agency for cleanup. That unlocks CDBG grant money to remove the structure and remediate the former mill site.

MeetingMar 3, 2026

Common Council - Mar 3, 2026

The demolition project is on track to finish by the end of March, with two extra structures added to the contract — including 21 Axon Street — paid from the demolition line.

MeetingFeb 17, 2026

Common Council - Feb 17, 2026

Ten of 23 blighted buildings are down, with the Lark and Swan Streets brick building currently being demolished — a site known for illegal dumping. All 23 should be done by April.

MeetingJan 6, 2026

Common Council - Jan 6, 2026

The federally funded demolition program starts the week of January 12, with Gorick Construction tearing down 23 structures citywide.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Amsterdam

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.