2026 Street Paving and Infrastructure Projects
Summary
The engineer will bring a draft street list next month and wants council members' ward requests by the end of February.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
2025 base bid was $1.35 million but came in under $900,000; about $2.7 million total available with $800,000 earmarked for the DPW garage.
Residents of streets selected for paving in 2026.
Residents whose streets don't make the trimmed list.
Mentions & discussions (4)
Common Council - Sep 1, 2026
Street paving continues for a few more weeks — Sloane Avenue gets about 700 tons of pavement — with the whole program done by early October. Golf cart path paving starts mid-September.
Common Council - Apr 7, 2026
The wish list of streets costs about 50% more than the roughly $2.3 million in CHIPS funding available. The City Engineer will rank streets by condition and traffic and report back by week's end.
Common Council - Feb 17, 2026
The Del Signore contract extension locks in 2025 prices and could get crews paving earlier in the spring. After setting aside roughly $800,000 in CHIPS money for the DPW garage demolition, about $1.9 million remains for actual street paving.
Common Council - Jan 6, 2026
The engineer will bring a draft street list next month and wants council members' ward requests by the end of February.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Amsterdam
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.