2026 street paving and Complete Streets progress
Summary
Another $725K bonded toward the $4.2 million Complete Streets project: East Main and Bridge Street work, an eventual Route 5 Eastbound closure, and turning Schuyler Street south of East Main into a two-way street.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
$725,000 in new bonding toward a $4.2 million project.
Drivers, pedestrians, and businesses around East Main, Bridge, and Schuyler Streets.
Drivers endured 15-20 minute delays during paving work.
Mentions & discussions (6)
Common Council - Oct 6, 2026
Upper Market Street and Northampton Road are done and shouldn't need repaving for a dozen years; Church, East Main and the arterials come next. One resident praised the smooth ride but suggested paving busy streets at night to cut delays.
Common Council - Aug 4, 2026
The $3.2 million contract award covers sidewalks, lighting and paving on Main Street from the mall to Stewarts, plus Bridge Street and Schuyler Street. It's a big visual and safety upgrade downtown.
Common Council - Jul 21, 2026
Paving starts next week; the Complete Streets bid opens Friday with DOT review after; National Grid is replacing gas mains on Northampton Road with repaving to follow; Broadway Hill reopens this week and the splash pad opens Friday.
Common Council - Mar 3, 2026
The city's paving contractor can start in May and dedicate May and June to Amsterdam — much earlier than usual. The engineer wants ward street lists ASAP.
Common Council - Feb 17, 2026
Alderman Carpenter floated a working group bringing together police, engineering, DPW, the school district and residents to tackle chronic traffic problems — speeding, dangerous intersections, parking — instead of handling them one-off. Interest gathering starts now.
Common Council - Feb 3, 2026
Another $725K bonded toward the $4.2 million Complete Streets project: East Main and Bridge Street work, an eventual Route 5 Eastbound closure, and turning Schuyler Street south of East Main into a two-way street.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Amsterdam
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.